应用桩基托换技术的深基坑工程下穿地铁高架桥变形控制研究

STUDY ON DEFORMATION CONTROL OF DEEP FOUNDATION PIT PROJECT UNDERPASSING SUBWAY VIADUCT USING PILE FOUNDATION UNDERPINNING TECHNOLOGY

  • 摘要: 针对道路深基坑下穿地铁高架桥工程中变形控制难的问题,该文依托北京某应用桩基托换技术的道路深基坑下穿既有地铁高架桥工程,采用数值模拟和现场实测相结合的方式,研究桩基托换和深基坑施工对地铁高架桥及轨道结构的影响,并对关键参数进行设计。结论如下:确定了主动托换的顶升力设计值、最优桩长、顶升千斤顶的选型及平面布置等关键技术;桩基托换阶段中,桥梁下部结构最大竖、横向变形分别为1.620 mm、1.904 mm,轨道结构最大竖、横向变形分别为1.877 mm、1.612 mm;基坑施工阶段中,桥梁下部结构的最大沉降为−2.982 mm、最大横向变形为2.530 mm,轨道结构最大沉降为−2.885 mm、最大横向变形为2.517 mm;邻近道路基坑处的桥墩变形对围护结构参数变化的敏感性大小为:围护桩嵌固深度插入比>围护桩桩径>围护桩桩距;该文研究可为类似地铁桥梁结构的变形规律及控制研究提供技术参考。

     

    Abstract: In order to solve the problem of difficult deformation control in the deep foundation pit project underpassing subway viaduct, this paper relies on the application of pile foundation underpinning technology to pass through an existing subway viaduct project in Beijing, and uses the combination of numerical simulation and field measurement to study the influence of pile foundation underpinning and deep foundation pit construction on the subway viaduct and track structure, and the key parameters are designed. The results show that: The key technologies such as the design value of the jacking force, the optimal pile length, the selection and plane layout of the jacking jack for active underpinning are determined; In the pile foundation underpinning stage, the maximum vertical and transverse deformations of the bridge substructure are 1.620 mm and 1.904 mm, respectively, and the maximum vertical and transverse deformations of the track structure are 1.877 mm and 1.612 mm, respectively. In the foundation pit construction stage, the maximum settlement of the bridge substructure is −2.982 mm, the maximum lateral deformation is 2.530 mm, and the maximum settlement and maximum transverse deformation of the track structure are −2.885 mm, and the maximum transverse deformation is 2.517 mm; The sensitivity of the pier deformation at the adjacent road foundation pit to the change of the parameters of the enclosure structure is as follows: the embedded depth of the enclosure pile > the diameter of the retaining pile > the distance between the retaining piles; The research in this paper can provide a technical reference for the study of the deformation law and control of similar subway bridge structures.

     

/

返回文章
返回